The Australian government aims to develop the country’s hydropower and Pumped Hydro Energy Storage (PHES) as part of its Powering Australia Plan, which targets 82 per cent renewable electricity by 2030 and net-zero emissions by 2050. As part of decarbonisation plans, the government hopes to gradually retire coal and gas-fired power stations. Meanwhile, intermittent wind and solar power will require long-duration, dispatchable storage to maintain grid stability. For this reason, the Australian Energy Market Operator expects the demand for storage to increase significantly over the coming decades.
In February, the International Hydropower Association (IHA) and its Australian members released a comprehensive roadmap to accelerate the development of the country’s pumped-storage projects as part of broader green-transition aims. The Australian Energy Market Operator’s draft 2026 Integrated System Plan estimates that the country will need to develop 27 GW of storage by 2030 and 55 GW by 2050.
At present, Australia has around 8.5 GW of traditional and pumped hydropower in operation, from over 120 hydroelectric stations, which provide between 5 per cent and 7 per cent of the country’s electricity. However, Australia has an impressive practical capacity of over 124 GW identified across potential project sites.
The president of the IHA, Malcolm Turnbull, stated, “Let me be clear: if we want a successful clean energy transition and affordable electricity for Australians, we’re going to need more pumped storage. It’s not optional—it’s essential. Pumped storage is the only proven technology that can store energy at the massive scale our grid requires. We have strong projects ready to go, but they need the right policy settings and market signals to get built.” In reference to the roadmap, Turnbull said, “The technology works. The economics work. What we need now is decisive action.”
ADVERTISEMENT
While developing Australia’s plan is expected to support its green transition and eventually reduce energy bills, development costs have been far higher than anticipated in some projects. The costs of Snowy 2.0, announced by then-Prime Minister Malcolm Turnbull in 2017 following plans to close several coal-fired power plants and amid backlash against wind farm development, have soared in recent years.
Snowy 2.0 would see an expansion of the Snowy Mountains Hydro-electric Scheme across New South Wales, Victoria, and South Australia, an energy project that includes 6 GW generating capacity across 16 power stations, 16 major dams, and an extensive network of tunnels and aqueducts. The aim was to create a massive, long-duration battery at an estimated cost of around $2 billion.
The project would develop a pump to move water uphill to a higher storage site during periods of low power demand and release it downhill to drive giant turbines and produce power for the grid during peak demand, particularly during low solar and wind generation hours. The expansion would increase the Snowy scheme by around 50 per cent by linking two reservoirs via tunnels of around 27 km to establish a 2.2 GW pumped hydro project with 350,000 megawatt-hours of storage. In 2017, operators estimated the project could take anywhere between four and seven years to complete.
Several challenges arose during development, leading to a substantial rise in project costs over the past nine years. A 2017 feasibility study suggested the project would cost between $5.4 billion and $6.9 billion to develop. The government ultimately made a $6.1 billion investment decision in 2018, even before geological studies were completed or approval for environmental works or transmission lines had been granted.
The project was approved in 2020, and three tunnel-boring machines were commissioned. However, little progress was seen in the following years. Meanwhile, one machine got stuck after hitting unexpected soft ground just 150 metres into a 15-kilometre excavation, and remained there for almost a year. Once operational again, it became stuck several more times.
In 2023, the new Labour government introduced an incentivised contract structure for new operators, the Italian industrial company Webuild, to carry out the project. However, tunnel workers went on strike over pay and working conditions, further delaying the project’s progress. By August that year, the projected cost had doubled to $12 billion, with a new estimated completion date of 2028.
ADVERTISEMENT
By this October, the projected cost of the project had soared to between $22.2 billion and $25 billion, with an expected completion date of 2029. Meanwhile, over a third of the tunnelling still needs to be completed as part of the expansion. The delays and cost increases did not come as a total surprise, as a 2020 independent review, which fell on deaf ears, had already suggested they would.
Developing Snowy 2.0 would help provide a steady electricity supply to a region heavily reliant on intermittent renewable energy sources, reducing reliance on fossil fuels. However, inadequate planning has led development costs to soar as the timeline extends. The development of such an ambitious pumped-hydrogen project has demonstrated the need to conduct extensive assessments to effectively plan for development and to help meet the government’s green transition goals.
By Felicity Bradstock for Oilprice.com